Start Date: March 2018
Anticipated Completion Date: June 2020
Total Estimated Cost: $160,000,000 in three separate phases
Partners: Preservation of Affordable Housing and Boston Housing Authority
Anticipated Start Date: 2024
Anticipated Completion Date: 2026
Total Estimated Cost: $80,000,000
Partner: Trinity Financial
Homeownership Units: 32
Rental Units: 64
Achieved Project Milestone: BPDA Article 80 Approval in May 2022; Zoning Board of Appeal approval in April 2023
Anticipated Start Date: 2024
Anticipated Completion Date: 2025
Partner: Urban League of Eastern Massachusetts
Homeownership Units: 22
Rental Units: 43
Achieved Project Milestone: Boston Planning & Development Agency Article 80 Board approval in August 2022 and Zoning Board of Appeal approval in December 2022
Total Estimated Cost: $50,000,000
Start Date: 2025
Anticipated Completion Date: 2026
Total Estimated Cost: $10,600,000
Homeownership Units: 15
Achieved Project Milestone: Developer Designation Extended in June 2022
Anticipated Start Date: 2026
Anticipated Completion Date: 2028
Total Estimated Cost: $50,000,000
Homeownership Units: 10-12
Rental Units: 40-60
Achieved Project Milestone: Architect selected, schematic design and community advisory process initiated
More info here: https://www.639warren.org/